| June 25th, 2008 Meeting Summary-- see also the 
	May 28, 2008 meeting summary 
			
			1) In attendance 
			Norah Gaynor, KC Parks; Herb Bone, 
			Marymoor R/C Club; Jack MacKinnon, Community Gardens; Greg Helland, SODA; Michael 
			Hobbs, East Lake Washington Audubon Society 2) Marymoor Map - Project Update 
			
			Matt has not presented a new draft... 3) Project Updates 
	
	
		
			Ahead of schedule - The notice to proceed was issued on June 
			23rd.  Materials are being staged in the middle of the park. 
			Mowing out to the east edge of the park is beginning.  Paving 
			may be as early as September.   The company with the contract has done this kind of work before, 
			and done it very well according to reports. 
		Ballfields 1 & 2 / Multiuse 
		
			Fields will close July 21st, but work will begin July 8th with 
			survey work and wetland mitigation.  Work is scheduled to be 
			complete January 2009.  If the fields themselves are completed 
			early, they may be open for soccer in November/December. Baseball fields are shifting to using artificial, removable 
			pitching mounds instead of dirt mounds. 
	
		
			Still dealing with parts issues, as some custom parts were damaged 
			in shipping.  The contractor is working with a local builder to 
			try and remanufacture the parts.Fire alarms are now up to code.  
			A security system will be in place soon. 
	
		
			Should be completely done and open by end of June, other than the 
			barriers to "close" the breaks in the wall between the Pet Garden 
			and the Community Garden.  A gate will be installed at the 
			access road at the northeast corner of the pet garden. 
	
		
			Opening Day - August 2.Weed pulls are ongoing, interpretive signs 
			will be going up, etc. Bike racks will be installed at each kiosk.  Norah passed 
			around a photo of a bike rack designed by the artist that will be 
			designing the racks for here (though not the design that will be 
			used in the park).  Greg mentioned that the rack didn't even 
			look like a bike rack, and that maybe BIKE RACK should be embossed 
			in the concrete mounting pad (or something). Work rules have been clarified; ELWAS can use hand tools and 
			light power tools including weed eaters.  This will allow the 
			Audubon Society to maintain the trail better. The boardwalk extension is scheduled to be completed before 
			August 2nd.  Prebuilt boardwalk sections will be ferried from 
			the Rowing Club across the slough. Next 
		meeting, Wednesday, July 23, 2008. 
	 These notes were made by 
	Michael Hobbs, and they do not constitute an official record of the
meeting.  They may have inaccuracies and omissions.  If anyone has any
complaints about the content of these notes, they should direct them to Michael
Hobbs at fomp@marymoor.org, and he will endeavor to
correct them.
 |