| February 25th, 2009 Meeting Summary-- see also the 
	January 28, 2009 meeting summary Attendees: Greg, Christina, Jenny (Parametrix) 
Norah, Herb, Tony, Steve (SRA)  East Lake Sammamish Trail – presentation by Jenny from 
Parametrix (last minute replacement) 
	Overall intent of the trail did not change from 
	original plan178 comments received to draft EIS – majority 
	approved. Those opposed were more focused on how to make the trail system 
	safe (similar to concerns expressed about Burke Gilman)Originally envisioned 5 phases2008 Phase: 30% design for entire trail and complete 
	portion in Redmond2009: construct trail segment in Redmond (roughly 
	from park to N. side of 520), complete design for Issaquah segment2010: construct segment in Issaquah, complete design 
	for Sammamish and south2011: construct south Sammamish segment and finish 
	balance of design2012: finish constructionFunding may require breaking project into additional 
	phases.Federal involvement (FHWA) has caused delays to 
	finalizing EISAdvertisement for construction can’t start until Fed 
	funding has been realized – hope to advertise in MayRisks to project schedule from appeals, political 
	change, increased project costsFEIS expected to be issued in April 2009Several other projects (some related) will be 
	starting near east end of park in next 6-8 months – trail construction 
	coordination will be paramount. Likely to have overall congestion impact.Updates provided on KC website (Jenny or Norah to 
	provide address).  Sammamish Rowing Association (SRA) 
	King Co lead entity for the permit applicationMarymoor staff were apparently not up to date either 
	on permit processQuestions from FOMP came up largely due to lack of 
	notice/informationRequested extension to allow time to review/comment 
	on application. Comment period runs through next week.Rowing association questions why the concern was 
	raised at all, given earlier information provided to group.Last presentation was believed to have been in March, 
	2008. Application materials submitted to Redmond are not substantively 
	different from what was presented at March 2008 meeting.1995 wetland map showed area south of existing 
	boathouse was not considered wetland. Original basis for permit application 
	was 1995 delineation map.Pursued initial permits under this premise.Had separate, recent delineation performed by 
	Watershed Company. New data indicated area south of boathouse was not 
	eligible for construction. Area north of boathouse also contained small 
	wetland areas that would limit construction opportunities.Slightly elevated area east of boathouse existed 
	after the remediation activities, and was identified by Watershed Co. as 
	non-wetland areaLarge cottonwood trees adjacent to proposed pad were 
	targeted by Redmond as trees that needed to be removed due to proximity to 
	construction site. Separate arborist report commissioned by SRA indicated 
	trees were healthy and should be able to survive construction.Submitted application documents through Redmond’s 
	“Prep” process, which allows applicant to vet technical information in 
	advance of formal application. Process worked well, per Rowing Association, 
	as allowed for a more iterative process for technical review.Mitigation was required by Redmond to be performed 
	within City limits, precluding mitigation in other parts of Marymoor (part 
	of King Co.). All mitigation will be performed in Marymoor West. • Submitted 
	for conditional use permit and shoreline permit in mid-Jan. Now in public 
	comment period.Re: size of parking lot compared to size of building: 
	highest use is mid to late afternoon when Juniors program is practicing. 
	Ultimate bottleneck is the size of the dock and the ability to accommodate 
	greater number of juniors. Have no intent to expand juniors program. 
	Therefore, parking lot size will not increase.Do, however, expect increase in other programs and 
	private boat storage and use, but these programs/individuals don’t use the 
	facility during the peak period.Rowing association would like to see FOMP support of 
	overall project expressed at public hearing (Monday, April 6). Michael is 
	party of record for notice.Mitigation monitoring runs for five years. Monitoring 
	period starts when certificate of occupancy is granted by City of Redmond.Old boathouse will be razed. Pad will remain and will 
	be used for outside storage of launches.Road also has to be widened in sections to comply 
	with Fire access requirements.Project also includes turn lane on W. Lk Sam Pkwy.Long-term Redmond plan includes acquiring 
	approximately 40 feet of park land along Parkway to accommodate road 
	widening and adjacent bike trail. Will eventually impact rowing club parking 
	lot, but date uncertain.FOMP requested copies of mitigation monitoring 
	reports once monitoring starts.  Microsoft Earth Day Projects (April 22) 
	Expect approximately 400 employees to work in park on 
	areas including birdloop, re-leaf and misc locations with invasive weeds.  CIP/Project updates 
	Park portion of Marymoor  Connector Trail 
	is open. Plantings have started. Will also, gradually, replace aged cherry 
	trees in road median.Ballfields largely finished. A few punchlist 
	items left to do, but fields will be open for use on 3/1.Pet Garden. No progress, so cookies provided 
	to the group. MCGA would like fencing completed within next couple of months 
	to limit dog access to fresh compost.Birdloop: Preliminary work done on the 
	boardwalk extension during work party 2/14. Planning another work party 
	Saturday, Feb. 28, to build the first section of the boardwalk. Plans 
	underway to use the help of Microsoft employees on Earth Day, April 22, to 
	complete the boardwalk.Clise: Dented fixture replaced. Other punch 
	list work in progress, should be all finished by next meeting.East Lake Sammamish Trail. See item 1. Will 
	leave on agenda for future updates.Roof Replacement: should happen this summer 
	with recycled or composite product. Structural assessment indicates barn is 
	in good condition with minimal updates required.Stage seating area: want hard surface to make 
	set-up easier. Gravel surface with plastic grid surface hasn’t been very 
	effective, and grid has aged beyond useful life. Parks doesn’t believe 
	gravel surface alone would be suitable. Porous concrete or asphalt is being 
	considered. Entire area is approximately 12,000 ft sq., and accommodates 
	1700 chairs. With stage now a permanent feature, pad in front is also 
	desired. Working on estimate for probable cost and exploring permit 
	requirements. Went from 1000 to 1700 chairs in 2008. FOMP requested drawing 
	to better evaluate scale of additional paved area.  Map  
	Parks incorporating final comments. Herb requested 
	minor modification related to coloring on R/C flying area.Core GIS (contractor) was paid half of overage from 
	original project budget. Balance of funds will be pursued through Parks.
	 Events/Activities: 
	Many new entries compared to last month. Norah to 
	provide updated list for posting to FOMP site.Cirque du Soleil probably in June/July/early Aug 
	2010. Hasn’t yet been confirmed, but highly likely.USGA Senior open will overlap end of Cirque. Parking 
	will be a premium  Other 
	Turnaround near MCGA still in Karl’s court. Will work 
	with Jack re: detailsMissing sign in MCGA parking lot on order 
	 Meeting adjourned at 9:12. Thanks to Greg Helland for these 
notes.  Please contact Greg if you have questions about them.If changes to these notes are required, please contact Michael Hobbs at
fomp@marymoor.org.
 Next 
		meeting, Wednesday, March 25, 2009 
 These notes do not constitute an official record of the
meeting.  They may have inaccuracies and omissions.  If anyone has any
complaints about the content of these notes, they should direct them to Michael
Hobbs at fomp@marymoor.org, and he will endeavor to
correct them.
 |